Waller High
School Expansion |
3/06/06
- All newly
constructed/renovated areas are occupied.
2/13/06
- The anticipated completion
date for the project is scheduled for February 28, 2006.
Notice to proceed was given to Gamma Construction on September
2, 2004.
1/09/06
- The front entry to the Fine
Arts Center is scheduled for completion the week of January
23rd-27th. Items remaining for completion include floor tile,
VCT, painting and various furnishings.
- The new gymnasium is scheduled
for completion the week of January 16th-20th. Basketball goals
and bleachers are currently being installed.
- The Performing Arts Center is
scheduled for completion by January 31st. The auditorium
seating, final coats of paint, miscellaneous stage lighting,
rigging and curtains are in the process of installation.
- The "ROTC" renovation area is
scheduled for completion the week of February 1st. Demolition
work and new construction of the spaces are running
concurrently.
- The Water Plant is scheduled
for completion February 28th. The galvanized water storage
tank delivery is scheduled for January 31st. The hydro-tank
has arrived on-site.
______________________________________________________________________________________________________________________
12/12/05
- Data cabling installation is
complete in the new Academic Addition. Waller ISD is
currently moving into this area.
- The wood floor in the new
Gymnasium has been installed and is currently in the process
of being sanded and sealed.
- The ceiling clouds at the
Performing Arts Center are installed. The entrance to
the Performing Arts Center is continuing as scheduled with the
arrival of glazing and storefront frames.
- The Fine Arts Center is
progressing as scheduled with Waller ISD currently moving into
this space.
- Renovation area scheduled for
the December break is currently being moved out of by Waller
ISD. Gamma Construction to proceed in this area once
given the go ahead by Waller ISD.
- Exterior walls and roof are
done at the Water Plant site. Exterior piping is stubbed
out to the tank and is ready for the water tank to arrive
onsite. The city is in the process of installing their water
line to building. CenterPoint is setting power
poles for the overhead electrical service.
|
11/14/05 |
-
Gamma Construction is finishing up all items on the
Athletic Annex punch list in preparation of re-walk
through with SHW and DBR.
-
Gamma Construction's cleaning crew is working in
preparation of the initial walk through with SHW. Data
cabling work is continuing during this cleaning
period. The majority of the new lockers are installed
in the new Academic Addition.
-
The painter has finished in the gymnasium excluding
some touch up areas. The wood flooring is on-site and
is acclimatizing in preparation for installation. The
bleachers are on site and waiting for the wood
flooring to be installed first.
-
Painting is continuing at the performing Arts Center.
Preparation for the theatre lighting and sound system
is complete. The entrance to the Performing Arts
Center is continuing as scheduled.
-
The Fine Arts Center is progressing as scheduled.
Ceiling grids have been installed along with light
fixtures. Ceramic tile, painting and the installation
of mill work is nearing completion. The front entry to
the school is continuing to be framed.
-
Gamma Construction is finishing up all items on the
renovation work punch list.
-
Exterior walls at the water plant are scheduled to
begin this week.
|
|
10/11/05 |
-
Gamma
Construction is finishing all items on the Athletic
Annex punch list in preparation of re-walk through
with SHW and DBR.
-
Air conditioning in the
new Academic Addition is up and running. Ceiling
tiles, floor tile, and VCT installation are nearing
completion. Carpet installation has begun. The
installation of marker boards is continuing.
-
The painter is continuing
to paint the interior of the new gymnasium. The wood
flooring has arrived on site and is acclimatizing in
preparation for installation.
-
Painting is continuing
at the Performing Arts Center. Electrical work in
preparation for the theatre lighting and sound system
is continuing. Work on the entrance to the Performing
Arts Center is continuing as scheduled.
-
The
Performing Arts Center is progressing as scheduled.
Ceiling grids and light fixtures have been installed.
Ceramic tile, painting, and the installation of mill
work continues. The front entry to the school is being
roofed and framed.
-
Gamma Construction is
finishing all items on the renovation work punch list.
-
Construction at the water
plant site has begun. Earthwork for the building pad
and the tank are progressing.
|
|
9/12/05 |
-
Gamma
Construction is finishing all items on the Athletic
Annex punch list in preparation of re-walk through
with SHW and DBR.
-
Air conditioning in the
new Academic Addition is up and running. DBR is
scheduled for an above-ceiling punch list the early
part of this week. Casework has been delivered and is
being installed inside the classrooms. Ceiling grids
and lights have been installed.
-
Work is beginning on the
front entry to the new gymnasium and the tie-in entry
to the existing school. Walls have been painted with
primer.
-
Drywall work is continuing
at the Performing Arts Center. VAV boxes are
installed. Roof and trim work is being finished in
this area and in the Performing Arts Center. Work is
continuing at the entrance to the auditorium.
-
The
Performing Arts Center is progressing as scheduled.
Ceiling grids and light fixtures have been installed.
Duct insulation is currently being installed.
-
Gamma Construction is
finishing all items on the renovation work punch list.
-
Water plant site has been
cleared by Gamma Construction as of 9/10/05. The road
to the site has been completed in anticipation of the
start of construction.
|
|
8/8/05 |
-
Gamma
Construction has received a punch list from SHW for
items requiring completion or touch up. This work will
be done at night and coordinated with the Athletic
director to avoid conflict with WISD Athletics. Hydro
mulch has been sprayed along the building's exterior.
-
Interior CMU walls are being primed for final paint
coat in the new Academic Addition. Work is continuing
in the new science lab areas. All MEP is continuing as
scheduled. Ceiling grids are currently being
installed.
-
Brick veneer installation
is almost complete at the new Gymnasium with the
exception of exterior pilasters. MEP work in this area
is almost complete.
-
Exterior walls are up and the majority of the
auditorium has brick veneer installed. Drywall
installation at the floor and ceiling level is
continuing. Installation of wall bracing along the
stage rigging side of the stage has begun.
-
The
Performing Arts Center is progressing as scheduled.
Drywall has been installed in the majority of the
rooms in this area.
-
Work
within the renovation area has been completed with a
few minor things left to do. Gamma Construction has
received a punch list from SHW for items requiring
completion or touch up. Gamma is working with school
administrators to avoid conflict with normal WHS
operations.
|
|
7/18/05 |
-
Athletic Annex is currently being moved into by WISD
coaching staff. Gamma Construction has received a
punch list from SHW for items requiring completion or
touch up. The work will be done at night and
coordinated with the Athletic Director as not to
conflict with WISD athletics.
-
The
block wall leave out at the new Academic Building has
been filled in. Sheathing and insulation has been
installed and is waiting for brick veneer
application.. All stairs to the mechanical mezzanine
along with exterior windows have been installed.
-
Brick veneer installation
is almost complete at the new Gymnasium, with the
exception of the block leave out for mechanical unit
access. This area, similar to the Academic Building,
will be built once all mechanical units have been
installed.
-
Exterior walls are up and the majority of the
Auditorium has brick veneer installed. Rough drywall
installation at the floor and ceiling level has begun.
-
The
Performing Arts Center
is progressing
as
scheduled. The connection between the new entry and
the existing entry has been framed in and the roof
system has been installed.
-
The
renovation of the main library and the main corridor
is progressing rapidly. Bulkheads and ceilings have
been framed in. All new interior walls have been
placed in both the library and the athletic renovation
area.
|
|
|
|
6/13/05 |
-
Progress at new Athletic Annex is proceeding as
scheduled. Interior finishes and millwork are
currently being installed, with the middle of July as
anticipated completion date.
-
Masonry at Academic Addition is 90% complete. Once
stairs arrive on site and are installed, block wall
leave-out will be constructed.
-
Exterior wall sheathing is almost complete and brick
veneer installation is beginning at the new Gymnasium.
Ductwork and drywall above 20'-0' is currently being
installed.
-
Steel work is almost complete at the Auditorium.
Exterior walls are up and have exterior sheathing on
them. The roof is approximately 90% installed in this
area.
-
The
Performing Arts Center
is progressing
as
scheduled. The building is almost dried in with the
exception of the Hi/Lo roof wall, which will begin
shortly. Brick work is continuing and the structural
connection to the existing corridor is nearing
completion.
-
Demolition work nearing completion inside the main
building with the exception of the mechanical
mezzanine.
|
|
|
5/9/05 |
-
Progress
at new Athletic Annex is proceeding as scheduled. Interior
finishes and exterior brick are being applied.
-
HVAC,
plumbing, and electrical work is progressing as scheduled.
Interior walls are currently under construction.
Mechanical units have been installed on mezzanine deck.
Exterior block work is 95% complete.
-
Steel
erection at the new Gymnasium is complete. Roof insulation
and roof deck are complete. Interior work at mezzanine and
interior wall construction has begun.
-
Masonry
walls are continuing to be constructed at the Performing Arts
Addition. Bar joists have been hung as far as possible to
this point.
-
Performing
Arts
Center
steel framing is continuing as scheduled.
-
Completion for all areas is scheduled for December 31,
2005.
|
4/11/05
-
Steel erection
and masonry are 98% complete at Athletic Annex. HVAC,
plumbing, and electrical work is 75% complete as scheduled.
-
Steel erection
of Academic Addition is 98% complete. HVAC, plumbing, and
electrical work are progressing as scheduled. Masonry walls
are under construction.
-
Steel erection
at the new Gymnasium is 98% complete. Roof insulation and roof
deck are complete.
-
Masonry walls
are under construction at the Performing Arts Addition.
-
Performing Arts
Addition steel framing is 50% erected.
-
Underground
utilities are 98% complete.
3/14/05 |
-
Concrete slab
is complete in all areas of the new additions with the
exception of mezzanine decks
-
Steel erection
is 98% complete and masonry is 85% complete at Athletic Annex.
HVAC, plumbing, and electrical work is progressing as
scheduled.
-
Steel erection
of Academic addition is 98% complete. HVAC, plumbing, and
electrical work is progressing as schedule
-
Steel erection
at the new Gymnasium is 80% complete. Roof insulation and roof
deck are being installed and progressing as scheduled.
-
Masonry walls
are being constructed at the Performing Arts addition.
-
Paving at the
Performing Arts addition is continuing as scheduled.
-
Underground
utilities are 95% complete.
-
Completion for
all areas is scheduled for December 31, 2005.
|
|
2/14/05 |
-
Concrete slab at Athletic
Annex is 100% complete, slab at Academic Addition is 100%
complete, slab at Gymnasium Addition is 100% complete, slab at
Performing Arts addition is 55% complete. (Auditorium slab expected to
be poured by 2/18/05.)
-
Steel erection of Athletic
Annex is 98% complete. Athletic Annex masonry is 40% complete.
HVAC, plumbing, electrical work progressing as scheduled.
-
Steel erection of Academic
Addition is 95% complete.
-
Paving at Performing Arts
addition
has begun.
-
Underground utilities are 85% complete.
|
|
11/9/04 |
 |
Construction on the new
addition to Waller High School on Fields Store Road is on time
and on budget according to Gamma
Construction Company Supervisor Mike Georges. |
|
|
Campus Improvements
by WISD Maintenance Department -
List |
 |
 |
|
|
|
Waller ISD Special
Education bus drivers (L-R) Dotty Bertleff and LA Williams use the new
WISD Transportation Training Room on April 21 to take the first aid and
bio hazards training required annually for all WISD bus drivers and
monitors.
FULL STORY |
Employees of Narramore
Glass of Waller replace a wall of windows in the original cafeteria of the
Waller Junior High West Campus as part of the remodeling project underway
by the WISD Maintenance Department.
FULL STORY |
|
|
 |
 |
 |
 |
|
Waller ISD Maintenance employees (L-R) Gary Rollins and Melvin
Stokely install the electrical supply for new heating units in the
ceiling of the original cafeteria in the Waller Junior High West
Campus.
FULL STORY |
Waller ISD Transportation Department Route Coordinator Karen
Breaux looks over the construction work being done by the WISD
Maintenance Department
FULL STORY |
Additional office space, restrooms, and other renovations added to
Transportation Building |
Fire alarm
systems were upgraded at WJH and HES.
|
 |
 |
 |
 |
Larger food
storage area added to JES cafeteria
|
New exterior doors added at JES |
New lockers installed at WJH East Campus |
New wall paneling was installed at SMS. |
 |
 |
 |
 |
|
Intercom systems were upgraded at WJH and HES. |
New exterior doors are being installed at RRE, SMS, and WJH. |
A new air chiller is added at WJH. |
440x30 feet of bus parking area added at the Transportation
Department. |
 |
 |
 |
 |
|
Old ceilings were
removed and replaced with new ceiling tiles in Waller Junior High
and Holleman Elementary School in June, 2004. |
WISD Maintenance Department employee Kinino Martinez works
on the new parking lot and sidewalk at Waller Junior High on May 6,
2004. |
WISD Maintenance
Department employees Howard Bennett, Melvin Stokely, and Gary Rollins
work on the electrical service upgrade for the bus barn on May 6, 2004. |
Over 13,000 feet of
additional parking area (enough for 30 cars) and a larger student
pick up and drop off area were added at RRE. |