- Citizens’ Facilities Planning Summation Committee
- Final Report
- February 19, 2007
|
|
2
|
- Nov. 14, 2006 a large group of community members gathered at Waller High
School where WISD Superintendent Richard McReavy shared the results of a
demographic study done by Population and Survey Analysts (PASA).
Following the meeting, three citizens’ committees were formed to
discuss:
- Financial Planning Committee
- Existing Facilities Planning Committee
- Capacity (enrollment, growth, and grade structure) Planning Committee
- During the months of Nov., Dec. and Jan. the committees met a total of 8
times and had multiple conversations with architectural and financial
consultants.
|
|
3
|
- Each committee was made up of WISD parents, community members,
administrators, teachers, board members, and consultants; they were
chaired by community members with the assistance of a WISD facilitator.
- Capacity (enrollment, growth, and grade structure) Planning Committee –
10 WISD representatives, 19 community members and parents, and 2
consultants
- Co-chairs – Brandi Gregg and Kathy Wachtendorf; WISD facilitator –
Danny Twardowski
- Existing Facilities Planning Committee – 17 WISD representatives, 12
community members and parents, and 2 consultants
- Chair – Herb Thomas; WISD facilitator Ray Stelter
- Financial Planning Committee – 6 WISD representatives, 15 community
members and parents, and 2 consultants
- Co-Chairs – Jerry Nickerson and Jimmy Henderson; WISD facilitator –
Mike Marcus
|
|
4
|
- Citizens’ Capacity Planning Committee (Enrollment, Growth, Grade
Structure & Capacity)
- Final Report
- February 19, 2007
|
|
5
|
- This Citizens’ Committee was charged with studying and evaluating:
- Projected Enrollment
- Growth Rate
- Grade Structure
- Capacity Targets/Optimal School Size
|
|
6
|
- The Committee challenged itself to:
- Keep the conversations child-centric
- Recommending a grade structure that afforded every student the
opportunity to achieve success
|
|
7
|
|
|
8
|
- Since 1976, WISD has modified its grade
- structure seven (7) times, primarily to
- address facility capacity issues.
|
|
9
|
- 1976 – 1980: K-6, 7-8, 9-12
- 1981 – 1984: K-4, 5-6, 7-8, 9-12
- 1985 – 1989: Information Not
Available
- 1990 – 1992: PreK-5, 6-7, 8-12
- 1993 – 1998: PreK-4, 5-6, 7-8,
9-12
- 1998 – 2002: PreK-3, 4, 5-6, 7-8,
9-12
- 2002 – 2006: PreK-4, 5-6, 7-8,
9-12
|
|
10
|
- Option 1: K-4, 5-6, 7-8, 9-12
- Option 2: K-5, 6-8, 9-12
- Option 3: K-5, 6-8, 9, 10-12
- Option 4: K-6, 7-9, 10-12
|
|
11
|
|
|
12
|
|
|
13
|
|
|
14
|
- Influence/impact that frequent student transition/turnover has on school
and sense of community
- Influence/impact that frequent student transition/turnover has on parent
involvement and participation
- Imposition of additional stress on students as a result of the frequent
school transitions
- Degradation of student achievement during each transition year they
experience (Note: Students
typically gain back the achievement loss in the year following the
transition year.)
|
|
15
|
- Nature of the role model younger students receive from older students
- Capacity of facilities
|
|
16
|
|
|
17
|
|
|
18
|
- High School: No impact until 2016
- Middle School: No impact until 2016
- Elementary School:
- 2009 – 1 new school needed
- 2012 – 1 new school needed
- 2016 – 1 new school needed
- ***According to PASA, if grade structure is NOT realigned, WISD will
need:
- 2009 - 1 new school
- 2011 – 2 new schools
- 2016 – 1 new school
|
|
19
|
- Elementary: 700-750 students
- Middle School: 900-1050 students
- High School: 2100-2250 students
|
|
20
|
- Realign grade structure to K-5, 6-8, 9-12
- This will better align with state curriculum
- Provide a better sense of community and parent involvement at campuses
- Reduced the need for two new schools in 2011 to one new school
|
|
21
|
- Citizens’ Existing Facilities Committee
- Final Report
- February 19, 2007
|
|
22
|
|
|
23
|
|
|
24
|
|
|
25
|
|
|
26
|
|
|
27
|
|
|
28
|
|
|
29
|
|
|
30
|
|
|
31
|
|
|
32
|
|
|
33
|
|
|
34
|
|
|
35
|
|
|
36
|
|
|
37
|
|
|
38
|
|
|
39
|
|
|
40
|
|
|
41
|
|
|
42
|
|
|
43
|
- Citizens’ Financial Planning Committee Final Report
- Feb. 19, 2007
|
|
44
|
|
|
45
|
|
|
46
|
|
|
47
|
|
|
48
|
|
|
49
|
|
|
50
|
|
|
51
|
- This is the optimum time for a bond program due to multiple elements:
- The retirement of old bonds
- Moody’s AAA Bond Rating
- Bond sales rates
- Increased value of property
- M&O rate decreasing due to state mandates
|
|